Arch00008.pngEditing Schedule Definitions

The Schedule definitions detail the column heading text, width, and border attributes for each record field being reported.

To edit a schedule definition:

  1. Select Tools > Reports > VA Records and Schedules.

  2. The Records and Schedules dialog box opens.

  3. Select the schedule to edit.

  4. Click Edit in the Schedules section of the Records and Schedules dialog box.

  5. The Edit Schedule Format dialog box opens. Specify the schedule appearance by selecting the column order and formatting.

  6. Click Options to edit the schedule font style and size.

  7. The Schedule Format Options dialog box opens; the current font type and size settings for the heading, subheadings, and body display.

  8. If different font settings are desired, click the appropriate Change button to open the Format Text dialog box and modify the font type and size for the heading, subheadings, and body of schedule items. (See Formatting Text.)

  9. Click OK to close the Schedule Format Options dialog box, and then click OK to close the Edit Schedule Format dialog box.

  10. Click Done to close the Records and Schedules dialog box.

~~~~~~~~~~~~~~~~~~~~~~~~~