Arch00045.pngChanging the Panel Schedule Format

To format a panel schedule:

  1. Select Tools > Reports > Create Panel Schedule.

  2. The Create Panel Schedule dialog box opens.

  3. Select the panel schedule and its location.

  4. Click Edit.

  5. The Schedule Formatting dialog box opens. Select the schedule to format from the Schedule list. A list of available fields and, if applicable, the schedule’s printed name displays.

  6. The columns shown in the Column Order list appear in the schedule in order.

    Panel schedule formatting is stored as a worksheet named “Panel Schedule Fmt.” This worksheet can be imported, using the Resource Browser, into other files where the same formatting is desired.

  7. Click OK to return to the Create Panel Schedule dialog box. Click OK to place the schedule with the specified format.

~~~~~~~~~~~~~~~~~~~~~~~~~